COMPENSATION FOR PART-PERFORMANCE IN LUMP-SUM CONTRACTS: AN ANALYSIS OF THE INTERPLAY BETWEEN THE PRINCIPLE OF QUANTUM MERUIT AND SECTION 70 OF THE INDIAN CONTRACT ACT, 1872 BY - SHASHWAT DHYANI
COMPENSATION FOR PART-PERFORMANCE
IN LUMP-SUM CONTRACTS: AN ANALYSIS OF THE INTERPLAY BETWEEN THE PRINCIPLE OF
QUANTUM MERUIT AND SECTION 70 OF THE INDIAN CONTRACT ACT, 1872
AUTHORED BY - SHASHWAT DHYANI,
ADVOCATE
LL.B., BSC. (HONS) PHYSICS
LL.B., BSC. (HONS) PHYSICS
ABSTRACT
The remedy available under the
principle of Quantum Meruit is well established and settled vide various
judicial pronouncements. This remedy is ostensibly available to those who have
executed some work or rendered any services for another in the absence of any
contractual relationship and/ or obligations. In fact, this specific absence of
any rights and obligations arising out of a valid contract is what necessitated
the development of this principle which stands statutorily envisaged under
Section 70 of the Indian Contract Act, 1872. As the title of the article
suggests, the primary aim of the Author is to analyse the interplay between the
legal principle and the statutory provision through the various judicial
pronouncements in India throughout the years. However, in addition thereto, the
Author also briefly attempts to shed light on a lacuna qua the
applicability of this principle to a unique situation arising, especially in lump-sum
construction contracts, wherein prior to the termination of such contract, there
has been part performance of the work and the question arises as to how the
party performing such work would be compensated, in the specific absence of any
price/ compensation fixed for that particular component of the scope of work.
Keywords: Quantum Meruit, Section 70 of the
Indian Contract Act, 1872, Part-performance of a contract.
INTRODUCTION
1. As per Black’s Law Dictionary[1],
the term ‘Quantum Meruit’ is defined as 'as much as he deserved'.
To put it more simply, the term refers to a reasonable compensation that should
be provided, or rather, that one is lawfully entitled to for performing some
work and/ or rendering any services, not intended to be done gratuitously. The
principle of Quantum Meruit is based on the rationale that a party who has put
in some work for the benefit of another party, albeit in the absence of
an express contractual relationship/ obligation, must still be compensated with
reasonable remuneration commensurate to the benefit enjoyed. The basis of such
compensation would be directly proportional to the benefit that has accrued to and/
or enjoyed by the party for whom anything is done/ delivered[2]. However,
in order to give a more detailed perspective, it may be easier to outline the
circumstances which gives rise to the need for relying upon such a principle.
2. Imagine a scenario where a contractor
(the party who has undertaken some work) has entered into a contract
with an employer to perform certain work and/ or render certain services. In
case, the employer breaches any terms of the contract, the contractor may seek
compensation qua such breach by way of liquidated damages and/ or
unliquidated damages contemplated under Section 73 or Section 74 of the Indian
Contract Act, 1872 (“Contract Act”), whichever may be applicable. However, the
question arises that in situations where prior to the untimely termination of
the contract due to reasons not attributable to the contractor, the contractor
has been made to perform certain extra[3]/
additional work by the employer, which was outside to the scope of the original
contract, how would the contractor be compensated for such additional work done?
The evident obstacle in such a case would be that such work that has been executed
by the contractor was not within the ambit of the extant contract and
consequently, there would be no provision under the contract providing a way
for the contractor to be compensated for such additional work done. To counter
this precise predicament, the principle of Quantum Meruit is relied upon which is
in the nature of an equitable remedy aiming towards compensating such contractors
for work done in the absence of any specific contractual relations/ obligations
between the parties involved. Such absence of a contractual relationship
between the parties, where certain work has been done, generally comes within
the ambit of “Quasi-Contracts”, giving rise to certain legal
implications, so that the party which has done the work has a remedy available seeking
adequate compensation in relation thereof.
3. A necessary corollary to the above
exposition may be a situation contemplated under Section 65 of the Contract Act,
which envisages that in case an “agreement is revealed to be void or becomes
void, anybody who earned any advantage or benefits from it is obliged by law to
reinstate it or reimburse the individual who received it.” However, as the
Title of the present article suggests, the author shall be focusing primarily
on Section 70 of the Contract Act.
SECTION 70 OF THE INDIAN CONTRACT
ACT, 1872
1. In India, a claim under Quantum
Meruit is statutorily enshrined under Section 70[4] of
the Contract Act. As stated hereinabove, this provision is ostensibly based on
the doctrine of Quantum Meruit; however, the provisions of the Contract Act carry
a more liberal interpretation; the principle of the section being wider than
the principle of Quantum Meruit[5]. A
bare perusal of the said provision categorically reveals that three conditions
need to be fulfilled before the benefit of this provision can be invoked by a
person. Firstly, a party should either lawfully do something for another person
or deliver something to him. Secondly, while doing or delivering something, the
party must not be acting gratuitously and thirdly, the person for whom
something is done or to whom something is delivered must have enjoyed the
benefit thereof. In such a case, the party who has enjoyed the benefit of the
work done and/ or goods delivered, is obligated to compensate the other party
for the same. Reliance is placed on State of W.B. v. B.K. Mondal and Sons[6], wherein
the Hon’ble Apex Court held that:
“14. It is plain that
three conditions must be satisfied before this section can be invoked. The
first condition is that a person should lawfully do something for another
person or deliver something to him. The second condition is that in doing the
said thing or delivering the said thing he must not intend to act gratuitously;
and the third is that the other person for whom something is done or to whom
something is delivered must enjoy the benefit thereof. When these conditions
are satisfied Section 70 imposes upon the latter person the liability to make
compensation to the former in respect of, or to restore, the thing so done or
delivered….”
JUDICIAL PRONOUNCEMENTS ON THE
APPLICABILITY OF THE PRINCIPLE OF QUANTUM MERUIT AND SECTION 70 OF THE CONTRACT
ACT:
1. Through various judicial
pronouncements, the Hon’ble Apex Court as well different High Courts in India
have done well to settle the position vis-à-vis the applicability of
Quantum Meruit and Section 70 of the Contract Act. In the case of Food
Corporation of India and Ors. v. Vikar Majdoor Kamdar Sakhari Mandli Ltd.,
[(2007) 13 SCC 544], the Hon’ble Apex Court held that:
“19…. A person who does work or who
supplies goods under a contract, if no price is fixed, is entitled to be paid a
reasonable sum for his labour and the goods supplied. If the work is outside
the contract, the terms of the contract can have no application; and the
contractor is entitled to be paid a reasonable price for such work as was done
by him.
20. If a party to a contract has done
additional construction for another not intending to do it gratuitously and
such other has obtained benefit, the former is entitled to compensation for the
additional work not covered by the contract. If an oral agreement is pleaded,
which is not proved, he will be entitled to compensation under Section 70.
Payment under this section can also be claimed for work done beyond the terms
of the contract, when the benefit of the work has been availed of by the
defendant.”
2. In Michigan Engineers Pvt. Ltd.
v. Municipal Corporation of Greater Bombay, [(2016) SCC OnLine Bom 2173], the
Hon’ble Bombay High Court held that:
“21. … The extension of
principle of quantum meruit, in the facts and circumstances, rightly made and
therefore, the award ought not to have modified as done by the learned Judge.
There was no express provision with this regard though two methods were
provided under the contract of payment. As directed and permitted, the
Appellants completed the work and agreed by both the parties to refer the
decision to the Arbitrator, itself means and shows that there was no fixed
contractual rights agreed and fixed by the Appellants and/or by the parties, as
there was no express terms of contract in this regard and specifically about
the rates. The decision so taken by the learned Arbitrator, ought not to have
been faulted with, as the amount was not towards the liquidated damages and/or
compensation, but for the actual work done under the supervision of the
Respondents. The findings, therefore, so given by the learned Arbitrator in
no way can be stated to be perverse and/or required to be interfered with by
the learned Judge. [Associate Builders (supra)]. It is relevant to note that
the Respondents never stopped and/or asked the Appellants not to work unless
the rates are settled by agreement. On the contrary, as recorded, permitted to
work and/or proceeded with the work by one method out of two so available with
further agreement to refer the Executive Engineers decision to the Arbitration.
Therefore, the issue of rate was not decided finally and/or agreed by and
between the parties and left for the Arbitrator to adjudicate the same. The
learned Arbitrator, as recorded, accordingly adjudicated and awarded the
reasonable compensation….”
3. Further, the Hon’ble High Court of
Guwahati in NHPC Ltd. v. Oriental Engineers, [2016 SCC OnLine Gau 60] as
regards Section 70 of the Act observed as follows:
“31. It is settled law that in a case
where the contract agreement does not specifically provide for compensating
reasonably for the work done by the contractor, the principles of quantum
meruit would be applicable. …”
4. In
view of the judgments referred to above, it is no more res-intergra and
has been duly settled that in case the work done by a party is outside the
scope of the contract or if no price specific price is fixed in terms of which
the party can be compensated, the contractor is lawfully entitled to be paid a
reasonable sum for such additional work done. In view thereof, by way of
invoking Section 70 of the Contract Act and relying upon the principle of
Quantum Meruit, the relevant party may seek reasonable and lawful remuneration for
the extra/ additional works done, provided the same is beyond the scope of the
contract, and/ or for work done for which no price is fixed in the contract. It
is pertinent to note that the said extra work should not be gratuitous in
nature and the same should be executed in accordance with the instructions and/
or under the supervision/ awareness of the other party, which has in fact,
enjoyed the benefit thereof.
5. Moreover, an interesting observation
has been made by the Hon’ble High Court of Delhi in S. N. Nandy & Co.
v. Nicco Corporation Ltd., 2011 SCC OnLine Del 987 (“Nandy”),
wherein the Hon’ble High Court observed that even if the extra work done was
not authorised by the concerned employer, the same would still be liable to
compensate the party who has executed the extra work, if the employer accepted
such extra work done and enjoyed benefit of the same. In light of the said
judgement, the employers cannot cower behind the fact that no specific
authorisation was given for execution of the extra work, and mere acceptance
and enjoyment thereof, would be sufficient for an action seeking remuneration
by invoking the principle of Quantum Meruit and Section 70 of the Contract Act.
The relevant excerpt from Nandy judgement is reproduced below for
ready reference
“23. In the case before this Court,
though the plaintiff has not specifically pleaded the provisions of Section 70
of the Contract Act, nor has any issue been framed by the Court on its
applicability, he has pleaded all the ingredients necessary for invocation of
the aforesaid statutory provision. In the plaint, the plaintiff has repeatedly
alleged execution of extra work for the defendant.…. The
plaintiff has, thus, pleaded all the necessary ingredients of Section 70 of the
Contract Act by claiming that (i) he had executed extra works for the
defendant; (2) extra works executed by him were accepted by the defendant and
(3) he had not executed extra work gratuitously. The defendant could have
refused to accept the extra works/extra quantities executed by the plaintiff.
In that event, it would not have been liable to pay for them. But, the
defendant failed to do so and accepted these works. Therefore, even if it is
presumed that the defendant had not consented to pay for the extra work by the
plaintiff, it is obliged in law to compensate him for the extra works, which
were accepted by it, without any protest and without claiming that the
plaintiff will not be paid for those works.”
6. The above judgment was challenged
before the Division Bench of the Hon’ble High Court in M/s. Nicco
Corporation Ltd. V. M/s. S.N. Nandy & Co, [2011 SCC OnLine Del 4656] and
the Division Bench upheld the observations on Section 70 of the Contract Act on
the grounds that “…as a matter of fact the works were executed and accepted
by the defendant”.[7]
SITUATION WHERE WORK DONE/ SERVICES
RENDERED ARE PURSUANT TO THE TERMS OF THE CONTRACT AND THE CONTRACT PROVIDES
FOR THE CONSIDERATION PAYABLE IN RESPECT THEREOF.
1. It is pertinent to mention that one
of the major thresholds qua the question regarding the applicability of
the principle of Quantum Meruit is that the price for the work done or
services rendered should not be fixed under the contract and the same should not be pursuant to the terms
of a contract. It may be noted that Section 70 of the Contract Act falls under
Chapter V of the Act titled 'Of Certain Relations Resembling Those
Created by Contract', which ostensibly means that the provision would
be applicable in the absence of a specific contract dictating the rights and
obligations between the parties concerned. In such circumstances, where there
exists no contract in place or if there was one, the price of rendering the
services was not already agreed upon, the courts would be empowered to grant
reasonable compensation/ remuneration to the concerned party for the services
rendered.
2. In this aspect, it may be relevant to
refer and rely upon the judgment passed by the Hon’ble Apex Court in Mahanagar
Telecom Nigam Ltd. V. Tata Communications Ltd., [Civil Appeal No. 1766 of 2019],
wherein the Hon’ble Apex Court has distinguished between reasonable
remuneration under Section 70 of the Contract Act and compensation for damages
arising out of breach of the contract. The Apex Court observed that:
“2. Having
heard the learned counsel for both sides, one neat question arises before this
Court, which is, whether, when parties are governed by contract, a claim in
quantum meruit under Section 70 of the Indian Contract Act, 1872 [“Contract
Act”] would be permissible. Section 70 of the Contract Act reads as under...
This Section occurs
in Chapter V of the Contract Act, which chapter is headed, “of certain
relations resembling those created by contract”. There are five sections that
are contained in this Chapter. Each of them is posited on the fact that there
is, in fact, no contractual relationship between the parties claiming under
this Chapter.
For example, under Section 68, if a person incapable of entering into a
contract is supplied necessaries by another person, then the person who has
furnished such supplies becomes entitled to be reimbursed from the property of
the person so incapable of entering into the contract. Section 69 also deals
with a case where a person has no contractual relationship with the other
person mentioned therein, but who is interested in the payment of money which
the other person is 5 bound by law to pay, and who, therefore, pays it on
behalf of such person. Such person is entitled to be reimbursed by the other
person. Under Section 71, again, the finder of goods spoken of is a person who
is fastened with the responsibility of a bailee as there is no contractual
relationship between the finder of goods and the goods which belong to another
person. Equally, under Section 72, a person to whom money has been paid or
anything delivered by mistake or coercion must repay or return it, or else,
such person would be unjustly enriched. Here again, there is no contractual
relationship between the parties. It is in this setting that Section 70 occurs.
3. Further, in Alopi Parshad and Sons
Ltd. v. Union of India, (1960) 2 SCR 793, the Hon’ble Apex Court held:
“…It
is difficult to appreciate the argument advanced by Mr. Chatterjee that the
Agents were entitled to claim remuneration at rates substantially different
from the terms stipulated, on the basis of quantum meruit. Compensation quantum
meruit is awarded for work done or services rendered, when the price thereof is
not fixed by a contract. For work done or services rendered pursuant to the
terms of a contract, compensation quantum meruit cannot be awarded where the
contract provides for the consideration payable in that behalf. Quantum meruit
is but reasonable compensation awarded on implication of a contract to
remunerate, and an express stipulation governing the relations between the
parties under a contract, cannot be displaced by assuming that the stipulation
is not reasonable……”
4. From the afore-stated judgements, it
is clear that a sine qua non for invocation of Section 70 of the Contract
Act is that the work done and/or services rendered should not be in pursuance of
the terms of a contract where the price has already been fixed and/ or
contemplated.
CONUNDRUM
1. Even though the law regarding the applicability
of Quantum Meruit and Section 70 of the Contract Act has been definitively
settled through various judicial pronouncements, however, there is still a
lacuna which has managed to slip through the cracks and needs to be adjudicated
upon and conclusively settled by the Hon’ble Courts. This area of concern pertains
to the unique situation regarding applicability of the above principle qua
part performance of a contract.
2. Let us take an example: A party (contractor)
enters into a lump-sum contract with another party (employer) for
execution of certain scope of work having components ‘a’, ‘b’ and ‘c’. The
total contract price for execution of the entire works (i.e., a+b+c) is specified
under the contract itself. However, the price break-up for the individual
components is categorically absent. In such a case, for reasons attributable to
the employer, the contract is terminated prior to its completion and the
contractor is only able to execute component ‘a’ of the entire scope of work,
the question arises as to how would the contractor be compensated for the
portion of the work duly executed by the same? Would the principle of Quantum
Meruit be applicable to such a scenario and whether the contractor is entitled
to invoke Section 70 of the Contract Act? At first blush, it may appear that
the ingredients of Section 70 of the Contract Act would be satisfied in such a
case, namely, the contractor has lawfully done something for the employer,
which was not intended to be done gratuitously and the employer has attained
benefit thereof. Further, the price of the component is also not fixed under
the contract, thereby, attracting the applicability of the principle of Quantum
Meruit. However, can it be said that the work done (component ‘a’) was
not in pursuance to the terms of the contract?
3. In Mulamchand v. State of M.P.[8], the
Apex Court categorically denied the applicability of Section 70 of the Contract
Act in view of the existence of a contract. Further, in Alopi Parshad (Supra),
where the Hon’ble Apex Court observed that “Compensation quantum meruit is
awarded for work done or services rendered, when the price thereof is not fixed
by a contract.”. However, immediately thereafter the Hon’ble Court goes on
to state: “For work done or services rendered pursuant to the terms of a
contract, compensation quantum meruit cannot be awarded where the contract
provides for the consideration payable in that behalf.” The question arises
as to how the above two statements would reconcile in a situation where the work
done or service rendered is merely a component of the entire work, which is
however, in pursuance of and/or contemplated within the terms of the contract
and the price is only fixed for the totality of the work and not in respect of
a component thereof.
4. However, at this juncture, it may be
relevant to refer to the Treatise on the Law of Contract[9], where
the following has been elucidated vis-à-vis the principle of Quantum
Meruit: “…So, also if entire performance, according to the express
agreement, be rendered impossible through the fault of either party, the party
in fault will be liable on a quantum meruit, or other action on the case, the
compensation being graduated as far as possible by the terms of the express
contract.”
5. Further, the only judgment which has
somewhat expounded upon the afore-discussed issue is Krishna Menon v.
Cochin Devaswom, Board and Anr., [1962 SCC OnLine Ker 102] where the
Hon’ble High Court of Kerala observed:
“15. No claim in the nature of a
quantum meruit can be founded upon a contract which has not been performed,
unless the person who has a right to insist on its performance has elected to
accept some benefit resulting from its partial or defective performance, or the
circumstances are such as to show, in some other way, that a new contract has
arisen between the parties. This is further qualified by the doctrine that
where a contract has been only partly performed, the mere fact that the part
performance has been beneficial is not enough to render the party benefited
liable to pay for it; it must be shown that he has taken the benefit of the
part performance under circumstances sufficient to raise an implied promise to
pay for the work done, notwithstanding the non-performance of the special
contract. Thus, if a builder contracts to build and complete a house for a lump
sum payable on completion, and he partially builds the house, but fails to
complete it, the fact that the owner of the premises has resumed possession of
them does not entitle the builder to sue either on the special contract or for
work and materials; for the special contract has not been performed, and the
mere fact that the owner has taken possession of his own premises does not
afford an inference that he has dispensed with the special contract and made a
new contract to pay for the work actually done.”
CONCLUDING
REMARKS
1. Although, the judgment in Krishna
Menon (Supra) restricts its analysis to situations where the reasons
for the incomplete/ defective performance of the contract is attributable to
the party executing the works, however, what can be conclusively inferred from
the same is that the principle of Quantum Meruit can definitely be invoked in
such case, albeit, to a limited extent wherein “..the person who has
a right to insist on its performance has elected to accept some benefit
resulting from its partial or defective performance, or the circumstances are
such as to show, in some other way, that a new contract has arisen between the
parties.”
2. This leaves the question as to how
the principle of Quantum Meruit would apply in situations where the non-completion
of the entire works/ contract is due to reasons attributable to the party who
has extended/ issued the concerned lump-sum contract. In such a case, whether
the component of the work actually performed/ executed can entitle the party performing
the same to lawful remuneration from the other defaulting part under the
principle of Quantum Meruit, is an issue that need redressal and consideration
by the Hon’ble Courts so that the same can be finally and conclusively settled
through judicial pronouncements.
[1] Black’s Law Dictionary, 2nd
Edition (1910) @ page 975
[2] Pallonjee Edulkee & Sons v. Lonavala City Municipality,
[AIR 1937 Bom 417]
[3] Food Corporation of India and Ors. v. Vikar Majdoor Kamdar Sakhari Mandli
Ltd., [(2007) 13 SCC 544] @ para 21: “The term 'extra' is generally used in relation to the works, which are not
expressly or impliedly included in the original contract price, provided the
work is within the framework of the original contract. The question whether a
particular work is extra will depend upon the terms and conditions of the
contract, and other documents connected therewith”
[4] Section 70 of the Contract Act:
Obligation of person
enjoying benefit of non-gratuitous act.
—Where a person lawfully does anything for another person, or delivers anything
to him, not intending to do so gratuitously, and such other person enjoys the
benefit thereof, the latter is bound to make compensation to the former in
respect of, or to restore, the thing so done or delivered.
[5]Food
Corporation of India and Ors. v. Vikar Majdoor Kamdar Sakhari Mandli Ltd., [(2007) 13 SCC 544] @ para 19
[6] [AIR 1962 SC 779]
[7] @ para 16, M/s. Nicco
Corporation Ltd. V. M/s. S.N. Nandy & Co, [2011 SCC OnLine Del 4656]
[8] Mulamchand v. State of M.P., [(1968) 3 SCR 214], the Apex Court observed that: “6...in a case falling
under Section 70 the person doing something for another or delivering something
to another cannot sue for the specific performance of the contract, nor ask for
damages for the breach of the contract, for the simple reason that there is no
contract between him and the other person for whom he does something or to whom
he delivers something…”.
[9] Vol. 1, page 11, para 18, Treatise
on the Law of Contract, William Wetmore Story